Thursday, January 20, 2011

Charlton Cottage Update

Speaking of 521 E. Charlton, demo inside the house has begun and the ceilings are out. You'll recall that the rafters will be exposed throughout the house. It looks 100% better already and we'll even take out the construction debris from the floor with a good offer.

Wednesday, January 12, 2011

The March of Progress

The foundation is complete at 528 E. Duffy. For those of you fascinated by foundations, this particular type requires the plumbers to do some rough in at the same time the concrete is being poured. Note the white PVC drain lines. At 414 E. Duffy we used a slightly different foundation system, but as there's very little difference in the finished product, we thought we'd try this to see how it compared. One difference with this slab is that there is no flooring system. In other words, for hardwood floors a subfloor needs to be glued down then solid hardwood floors would then be nailed into the sleeper system subfloor. You could also do engineered floors simply by gluing them directly to the slab. Next we'll start framing.

Over on 521 E. Charlton the back yard has been cleared for the parking.

BEFORE:














AFTER:















The backyard has now been leveled for the parking. This also gives us a place to put our dumpster. We'll be moving inside as soon as the permits are finalized.

Thursday, January 6, 2011

An Idea from Ikea

I spent Christmas week in Atlanta attempting to relax (naturally, work crept in). We did make a stop at Ikea, naturally, for ideas and a few odds and ends (may I recommend the Expedit bookcase at $39 http://www.ikea.com/us/en/catalog/products/60135299). While I didn't see this kitchen in the store, it's featured in the catalog and it has some appeal to me.

Ikea Kitchen:





























The kitchens at 313 E. Park and 528 E. Duffy are not dissimilar in layout, but have full cabinets in the front of the kitchen, whereas this kitchen has more of a open bar effect. I kind of like how it opens the space even further and it also seems a little easier to eat at, as well as being a great prep space. There's no lack of storage space because of the walk in pantry. I'd be curious to hear any thoughts on which option you would prefer in your kitchen. Keep in mind that there is a powder room in the rear of our kitchens and somehow a variation of the Ikea kitchen would need to incorporate space for the powder room.

313 E. Park Kitchen:

Wednesday, January 5, 2011

Project(s) Update

The good news is the foundation is being poured at 528 E. Duffy Street. You may or may not find the attached photos interesting, but it's all we have at the moment. Faithful readers will remember 313 E. Park Avenue which was always meant to be 528 E. Duffy's sister project. It was tied up due to some closing issues with the seller, but it looks like we should finally be able to start next week.















One project that, unfortunately, we won't be starting is 102 W. 31st Street. This came into play while we waited for the closing issues on 313 E. Park. Unfortunately, after we put it under contract we found out it had it's own closing issues (see my earlier post about title issues). Apparently these title issues will be protracted as it appears the quiet title action that the seller paid an attorney to perform was not properly recorded in the public records. The seller's not too happy about that and I wouldn't be either. If you pay someone to do a job and find out years later that they didn't do it correctly, that would be annoying, especially if it prevents you from selling your property. As for me, I still think it's a great property and we hope to build on it if the title issues can ever be rectified.

510 E. Waldburg is waiting for permits. There is a slight snag at the permitting department (notice how there is a number of "slight snags" happening at this particular time) but we expect to begin next week.















At 521 E. Charlton we'll be clearing and leveling the yard to create the off street parking this week.

Thursday, December 23, 2010

Charlton Cottage Update

BEFORE: Obviously the floor plans don't show the 8 foot ceilings, but one important component will be removing the ceilings and exposing the rafters. Right now you have two bedrooms, one bath and what's labeled as a "spare room."
















AFTER: In the new plan, the closet in the front bedroom will become a full wall of closets, as the master bedroom closet will incorporated into the front bedroom's space. There will be a cased opening from the master bedroom into what will become a bath suite. So there will be a full walk-in closet, a washer/dryer and then the bathroom, with a clawfoot tub. In the kitchen one window is going away, creating more upper cabinet space. There will also be an inglenook (built-in L-shaped bench seats and table) on the long wall opposite the cabinets.
















Click on the images above to view a larger version.

2010 Reader Remodel Winner: From Blank Slate to Charming Cape


By: Bibi Coyne, Homeowner, This Old House magazine

John and Bibi Coyne nabbed the top prize in This Old House's 2010 Reader Remodel Contest. Here's the story of their renovation:

Want to know what it's been like to fix up our little Cape? Picture my husband, John, and me up at midnight prying off door trim and sawing through plaster. We just had to widen that doorway. It was the only way to get our new fridge into the kitchen.

Eight years ago, we didn't own a Sawzall, much less know how to operate one. But that was also before we noticed flakes of spray paint sticking to our kids after bath time, thanks to an old cosmetic fix on the tub. And before that same bath's dripping faucet finally sent us over the edge, forcing us to redo the dismal room long before we wanted to. Yes, we ripped out the tub, and the faucet, too.

Continue reading at http://www.thisoldhouse.com/toh/photos/0,,20394980,00.html

Blogger Matthew Allan is a specialist in Savannah Real Estate, focusing on Savannah's downtown historic districts, including the Landmark Historic District, Victorian Historic District, Thomas Square Historic District, Starland Historic District, Baldwin Park, and Ardsley Park Historic District.

Wednesday, December 22, 2010

New Project!

The beginning of the year is going to be extremely busy. We have another project, this time on 510 East Waldburg Street. Despite my best efforts to avoid it, the project found me. It had previously gone under contract, but it fell through and the seller’s agent called me. We worked out a deal, which is closing tomorrow, and so off we go. This is an unusual house for the Victorian District, because it was built in a Mediterranean style in the 1930s. I don’t know whether there was an earlier house on the lot, which is sometimes the case with these homes that are later than the other homes in the neighborhood. It’s an upstairs/downstairs duplex, with 2 bedrooms and 1 bath and about 1250 square feet in each unit. The bedrooms are very good sizes for a home this age—about 12 x 12 ¾ for the larger and 12 ½ x 10 ¾ for the smaller bedroom. Each unit has a kitchen, breakfast room, separate dining room, living room, and a sunroom. For SCAD purposes, that sunroom could turn into a third bedroom, but a more elegant use would be as a den or office. The breakfast rooms will turn into laundry rooms, with extra pantry storage.

The house needs the usual suspects—upgraded plumbing, electric, new paint, new cabinets, HVAC. The HVAC, we hope, will be a slightly less involved ordeal, because there is actually central heat. Not sure why it’s just a central heat system without central air, but at least the ducting is in place. The hardwood floors appear to be in pretty good condition, and the hardwoods are still in place underneath the vinyl and linoleum in the kitchen and breakfast rooms. We have a bathroom floor that has seen too much water and needs to be rebuilt, but in general the structure appears to be solid. The upper unit also has an attic—did I mention yet we’ll be doing a new roof—which houses some ducting but also has plenty of room for storage.

I’m excited—the house in on a good block and we should be able to put in back on the market at an attractive price.

Front Exterior














Downstairs Living Room














Downstairs Sunroom














Downstairs Bathroom














Downstairs Breakfast Room (soon to be laundry room)




















Downstairs Kitchen














Downstairs Bedroom














Upstairs Living Room














Floor in Upstairs Dining Room














Upstairs Kitchen














Upstairs Bathroom




















Rear Exterior

Thursday, December 9, 2010

A New Renovation Project

If you’ve been waiting for a post with a little meat on the bones (not that we all don’t love This Old House’s best products of 2010), here we go. Lately I’ve started to feel like a straight-up homebuilder, considering the work on 414 East Duffy and our plans for 528 East Duffy, and now 102 West 31st Street. We’re still waiting for another lot on 313 East Park, which is tied up in some legal issues. But now I have a straight-up renovation on my hands, just like the old days. 521 East Charlton is in the Landmark Historic District, in the Beach Institute neighborhood. It’s an unusual house by the standards of the Landmark District, because it’s actually a small cinderblock cottage that was probably built in the 1940s or early 1950s, measuring about 900 square feet, with 2 bedrooms and 1 bath. There is carpet AND linoleum over the original hardwood floors, a funky little addition in the back, off the second bedroom, and very low ceilings. What, pray tell, is interesting about this house, then? For starters, it’s in a great location, just one block from Troup Square. It has a great yard with what will be 2 parking spaces. And there is very little inventory in the sub-$140k range, which is where we plan to market the finished product. It will also give me a change to work on a style of house that I haven’t done yet, which is a straight-up cottage. I’m thinking beadboard in the kitchen and baths, clawfoot tub in what will be the new second bath in the addition. Plus refinishing the original floors, adding HVAC, new plumbing and electric and tearing out the low ceilings and exposing the rafters. Should be a major transformation.

Image 1: Front Exterior















Image 2: Living Room (Yes, we will be replacing that weird old heater with central HVAC)














Image 3: Floor in Living Room (Hardwoods under three layers of junk)














Image 4: Bathroom (We'll need to jack up the floor a bit, not to mention EVERYTHING else.)



















Image 5: Bedroom #1 (This will turn into a full wall of closets because the next bedroom will have a walk-in closet of its own.)














Image 6: Kitchen (Picture new cabinets and appliances and a dining nook in that right back corner.)














Image 7: Floor in Kitchen




















Image 8: Soon to be Master Bath & Closet (This is the weird addition. Picture walking through a large closet into the master bath with clawfoot tub.)














Image 9: We'll be tearing out the ceiling and exposing these rafters.



















Image 10: Backyard (The lot is about 100 feet deep and the parking pad will be about 20 feet wide.)