Thursday, April 14, 2011

521 E. Charlton Update

We're ready now for our framing inspection, which means we will insulate and then drywall, so very soon these pictures will show a total different level of finish.


We've opened the 2nd window back up in the kitchen.














Hard to see unless you know what you're looking for, but we've flipped the position of the tub and the sink in the 2nd bath.














We still need to get rid of this clawfoot tub.














The carpet is up, but the linoleum is still down to protect the hardwood floors.














Another change, this will be a L-shaped piece of glass in the master bath shower.